hi all:
I am using Xilinx Virtex2 V6000 BF957 , ISE 5.1.03i.
Now I have met hold timeing violation after PAR.The error message is like
below:

TIMESPEC TS_CLKA = PERIOD CLKA_grp 60 ns HIGH 50% ;
TIMESPEC TS_CLKB = PERIOD CLKB_grp 60 ns HIGH 50% ;
TIMESPEC TS_CLKA_TO_CLKB = FROM CLKA_grp TO CLKB_grp 60 ns ;

Data path delay : 1.752 ns
Source clock : CLKA ; Destination clock CLKB
Clock Skew : 2.789 ns

Well , both CLKA and CLKB are global clock, they have the same frequence
and the same phase.
Three methods I could think out to correct this problem :
1) tp longer the data path ,
in pratice, the ISE should have known this , however my resources
usage is up to 95%, could this be the reason that the tool
failed to longer the data path to meet this timing constraint ?
2) to reduce the clock skew :
both clock are global global clock ,and have the same frequeces, but how
to write constraints to let the tool reduce the clock skew?
3) use only one clock with clock enable .
Well , this design is too large , and the worse is that most of the RTL
is not written by me , doing this really takes time .

I am looking foward to your response , any suggestion will be highly
appreciated!

--
BestRegards
Black Huang
 
Well, I forgot to mention that both CLKA and
CLKB are derived from a clk named CLKIN.In
practice, CLKA and CLKB are almost the same,the only difference is that when
in power down mode the CLKB is not generated!

--
BestRegards
BlackShark Huang
"BlackSim" <mini_monkey@163.net> wrote in message
news:bvllaa$u4p2l$1@ID-199450.news.uni-berlin.de...
hi all:
I am using Xilinx Virtex2 V6000 BF957 , ISE 5.1.03i.
Now I have met hold timeing violation after PAR.The error message is like
below:

TIMESPEC TS_CLKA = PERIOD CLKA_grp 60 ns HIGH 50% ;
TIMESPEC TS_CLKB = PERIOD CLKB_grp 60 ns HIGH 50% ;
TIMESPEC TS_CLKA_TO_CLKB = FROM CLKA_grp TO CLKB_grp 60 ns ;

Data path delay : 1.752 ns
Source clock : CLKA ; Destination clock CLKB
Clock Skew : 2.789 ns

Well , both CLKA and CLKB are global clock, they have the same frequence
and the same phase.
Three methods I could think out to correct this problem :
1) tp longer the data path ,
in pratice, the ISE should have known this , however my
resources
usage is up to 95%, could this be the reason that the tool
failed to longer the data path to meet this timing constraint ?
2) to reduce the clock skew :
both clock are global global clock ,and have the same frequeces, but
how
to write constraints to let the tool reduce the clock skew?
3) use only one clock with clock enable .
Well , this design is too large , and the worse is that most of the RTL
is not written by me , doing this really takes time .

I am looking foward to your response , any suggestion will be highly
appreciated!

--